Completed flood alleviation culvert at Venn Ottery
CIVIL ENGINEERING • FLOOD ALLEVIATION

Venn OtteryFlood Alleviation Scheme

Protecting a Devon community with an 8x increase in drainage capacity, delivered on time and on budget.

💧
300 L/s
Original Capacity
🌊
2,300 L/s
New Capacity
📈
8x
Capacity Increase
⏱️
6 weeks
Project Duration
PROJECT BACKGROUND

Protecting a Community from Flooding

For many years, the community of Venn Ottery experienced persistent flooding, most recently during the severe floods in May 2023. Investigations identified the primary cause to be an undersized culvert that struggled to cope with peak flows, resulting in frequent road closures, property flooding, and community disruption.

Working closely with Devon County Council engineers and the Environment Agency, we developed a detailed plan to replace the failed infrastructure while maintaining the natural flow of the stream throughout the works.

Client: Devon County Council

  • • Collaborative planning with DCC engineers
  • • Environment Agency coordination
  • • Community liaison throughout
  • • Full regulatory compliance
Culvert construction showing three drainage pipes
Concrete and reinforcement work in progress
ENGINEERING SOLUTION

Revised Design for Maximum Impact

When buried services prevented the original box culvert design, our team rapidly developed an alternative that actually improved hydraulic performance.

Technical Specifications

Three 600mm ductile iron pipes
Fully encased in concrete
Installed beneath the carriageway
Carefully routed around existing services
Rock armour erosion protection
Safety handrails and access provisions

Capacity Improvement

Original Capacity
300 L/s
New Capacity
2,300 L/s

This nearly eight-fold increase dramatically reduces the risk of future flooding and equips the system to handle extreme weather events far more effectively.

ON-SITE CHALLENGES

Adapting to Complex Site Conditions

Our ability to respond rapidly to unexpected challenges was critical to the project's success.

Buried Services

Early excavation revealed multiple buried services running directly through the footprint of the proposed culvert, many of which were immovable.

Our Solution:
Our site supervisor worked side-by-side with Devon's engineers to rapidly redesign a solution that would both increase drainage capacity and navigate the existing service constraints.

Original Design Change

The original design—an 18m long 1.5m x 0.5m box culvert—could not be installed as planned due to the service conflicts.

Our Solution:
Developed a new design featuring three 600mm ductile iron pipes, fully encased in concrete, carefully routed around existing services.

Maintaining Stream Flow

The natural flow of the stream needed to be maintained throughout the works to protect the environment.

Our Solution:
Implemented an over-pumping setup, diverting water safely around the site to keep the work area dry.

Severe Weather

Throughout the project, the crew worked through severe weather, including periods under yellow weather warnings.

Our Solution:
Despite challenging conditions, the team maintained progress and ensured works were delivered safely and to a high standard.

Project Outcome

On Time
Delivered within the 6-week programme despite weather challenges
On Budget
Completed within the agreed project budget
8x Capacity
Dramatically reduced flood risk for the community

Stakeholder Feedback

“Devon County Council expressed full satisfaction with the solution and the adaptability shown on site.”

— Devon County Council

“Local residents and Venn Ottery and Southerton Residents Association are extremely pleased with the outcome.”

— Venn Ottery & Southerton Residents Association

Need Civil Engineering Expertise?

From flood alleviation to drainage solutions, our experienced team delivers complex civil engineering projects on time and on budget. Contact us to discuss your requirements.